The battery plant was expanded and now has close to double the original capacity. An LVD was
also
installed and the repeater controller firmware was upgraded and re-programmed to allow us access
to
the latest features and improvements. ALL audio levels were also re-aligned which improved the
s/n
ratio and overall volume level/intelligibility across that entire segment of the network both
Northbound and Southbound. Some tower work and general preparedness for winter storms was also
initiated.
This site is in the middle of the path between the Bay Area and the Southland and we wanted to
make
sure it did not become the weak link during a power outage.
Finally, a lot of time was expended trying to get an avian drop in visitor to take the same back
door
to exit the building as the one it came in through so we could go home. That helped to make a
long 16
hour day of it all. Maybe next time we need to bring a fake Cat and Owl to the site(s) so we can