    CARLA 32 on extended battery power
    Last updated on January 23, 2016 by The C.A.R.L.A. Team | This article is Archived | Permalink

    The commercial power lines and transformer at the site suffered damage and are being worked on. However, heavy rains make the road impassable at times and hence an extended delay in making repairs. The site has been running on back-up battery power for nearly a week now. We anticipate an ETR of mid week sometime around January 27/28th time frame.

    We have taken the repeater off-line from the primary hub/network to conserve battery power. It is still linked to CARLA 33 up the coast since traffic is typically very light from that direction.